WattEV opens a heavy-duty charging depot at the Port of Oakland and puts its first Tesla Semis on Bay Area freight

The site can charge 25 trucks at once at up to 240 kW each, or seven trucks at 1.2 MW, and WattEV says more than 300 electric Semis will eventually run from Oakland to Sacramento, the Central Valley and Nevada.

A white Tesla Semi tractor parked outside Tesla headquarters
Photo: Steve Jurvetson, via Wikimedia Commons · CC BY 2.0

WattEV opened a heavy-duty electric truck charging depot at the Port of Oakland on Nov. 23, its eighth in California, and introduced the first of what it says will be a large fleet of electric Tesla Semi trucks serving the port.

The company, in a release issued Monday, called it Northern California's first public depot of its kind. The station is at 8407 Edgewater Drive in Oakland.

What the depot can do

According to WattEV, the station can charge:

  • 25 medium and heavy-duty electric trucks at the same time at up to 240 kW each, or
  • seven trucks at 1.2 MW

The company said the depot is designed for megawatt charging, which it said cuts charging stops to 30 minutes or less, close to the time it takes to fuel a diesel truck. Power comes from PG&E through its Flex Connect program, which the utility said connects sites to the grid faster by making better use of existing grid capacity instead of waiting years for upgrades.

300 trucks planned

WattEV said more than 300 electric Semis will form a zero-emission freight corridor from the Bay Area to Sacramento, the Central Valley, Nevada and beyond. It also said that at current diesel prices, the per-mile energy cost of the new electric trucks is lower than that of comparable diesel trucks. The release did not give per-mile figures.

"Until now, most truck charging infrastructure has been concentrated in Southern California," said Salim Youssefzadeh, WattEV's CEO and co-founder. "We're thrilled to enable zero-emission freight transport from key ports like Oakland and Stockton into Sacramento, Central California and Nevada."

Port of Oakland Executive Director Kristi McKenney said the port is "seeing real progress in transforming how our industry moves goods to and from the Oakland Seaport." The port begins its centennial next year.

The rest of the network

The Oakland site joins seven WattEV depots already operating at the Port of Long Beach and in Bakersfield, San Bernardino, Gardena, Vernon, Oxnard and Fresno. Representatives of the City of Oakland, the Bay Area Air District, the California Energy Commission, the California Air Resources Board and PG&E attended the opening, the company said.

Up next

Durable goods orders edge up 0.2% in October as machinery climbs 1.8%, Census says

New orders reached $346.7 billion and shipments rose 0.5% to $338.6 billion. Orders for motor vehicles and parts gained 0.9%, while transportation equipment overall slipped 0.3%.

U.S. economy grew at a 4.3% rate in the third quarter, BEA says, as October spending on goods rose $11.8 billion

BEA revised third-quarter growth up 0.9 point. In October, inflation-adjusted consumer spending dipped slightly while PCE prices ran 3.8% above a year earlier.

Minnesota is 1,602 truck parking spaces short, with about 700 of the gap in the Twin Cities, MnDOT study finds

The state counts 4,620 spaces at 205 locations, and 82% of them are privately run. MnDOT wants public-private deals and a new regional lot for the metro area.