Trucks over 22 feet or 8,000 pounds can't ride Washington ferries to Orcas Island until cracked terminal beams are fixed
Washington State Ferries says repairs could take up to two weeks, and San Juan County is pointing freight to commercial barges in the meantime.

Trucks longer than 22 feet or heavier than 8,000 pounds are shut out of ferry service to and from Orcas Island in Washington's San Juan Islands while crews repair cracked steel beams at the island's ferry terminal.
Washington State Ferries (WSF) said engineers found cracks in two steel beams, called stringers, beneath the transfer span at the Orcas terminal during a routine inspection. The transfer span is the movable section of the dock that raises and lowers to meet the boat so vehicles can drive on and off. The cracks were found under one of the wheel paths.
The limits
Under restrictions that took effect Monday, Nov. 9, only vehicles shorter than 22 feet and lighter than 8,000 pounds can load or unload at Orcas, according to the WSF service bulletin. Terminal staff may turn away a vehicle they judge to be over the weight limit.
- Vehicles over 22 feet or over 8,000 pounds bound for Orcas will not be loaded at Anacortes, Shaw, Lopez or Friday Harbor.
- Vehicles that do cross must keep to 5 mph and stay on the east side of the terminal bridge.
- Customers holding reservations for vehicles 22 feet and longer will not be charged no-show fees.
How long
In a Nov. 10 update on the WSDOT blog, the agency said repairs are expected to take up to two weeks. Design work is complete, and crews will use bolted connections and steel plates instead of welding to speed the job. A contractor began installing scaffolding Nov. 10.
WSDOT said it is looking at ways to shorten the timeline and to let larger vehicles cross before final repairs are done. The ferry system's bulletin, last updated Nov. 12, said it expected an update on the repairs on Friday, Nov. 13.
Freight moves to barges
San Juan County said the disruption will significantly affect Orcas businesses that depend on the ferry for goods and services. Several commercial barge operators are adding capacity, with priority for essential loads including food, medical supplies, fuel, sanitation supplies and mail and package delivery.
The county asked residents to use caution between Eastsound and Olga, where it expects more commercial truck traffic on local roads. It said it is also exploring state assistance for affected businesses. WSF said owners of larger vehicles stuck on the island can ask terminal staff about parking options.
More work in 2027
Separately, WSF plans to replace the major mechanical and electrical systems of the transfer spans at Anacortes, Lopez and Orcas in early 2027. That project includes a 48-hour closure of the Orcas terminal on March 9 and 10, 2027.